Davis Langdon LLP are appointed for the first phase of the development of the Lower Stoke Works in Coventry. This phase will consist of the Peugeot Campus and associated road and service infrastructure for all future phases.
On completion, the former Peugeot accommodation will be demolished and cleared for a local shopping and amenity centre and up to 1700 new dwellings.
Peugeot Head Quarters Building
Site Area: 7.44 Acres
Floor Area: 130,392sq ft
Cost: £17m
Form of Contract: JCT with Contractor’s Design, 1998 Edition
Contract Period: 12 months
Occupation: July 2007
The project also comprises:
- £3m Technical Centre
- Infrastructure for the Peugeot Campus & 1700 new dwellings
- Pavilion and sports pitches
Programme:
November 2005 – issue of tender documents
March 2006 – enter into contract
April to October 2006 – Enabling works and infrastructure works
July 2006 to March 2007 – Construction of Technical Centre
July 2006 to July 2007 – Construction of Head Quarters Building